[NRAO logo]
NRAO logo  


[NRAO dedication, 1957]
NRAO dedication, 1957. NRAO/AUI image


[Dedication of the 85 foot Tatel telescope]
85 foot Tatel Telescope dedication, 1958. NRAO/AUI image


[85 foot Tatel telescope]
85 foot Tatel Telescope. NRAO/AUI image


[Struve at groundbreaking for 300 foot telescope]
Struve at 300 foot ground breaking, 1961. NRAO/AUI image


[300 foot telescope]
300 foot telescope. NRAO/AUI image


[140 Foot telescope ground breaking]
140 foot telescope ground breaking, 1958. NRAO/AUI image


[NRAO 140 Foot telescope]
NRAO 140 Foot telescope. NRAO/AUI image


[Green Bank Interferometer]
Green Bank Interferometer. NRAO/AUI image


[VLA dedication]
VLA dedication, 1980. NRAO/AUI image


[VLA]
VLA. NRAO/AUI image


[AIPS logo]
AIPS logo. NRAO/AUI image


[VLBA Pie Town antenna]
VLBA Pie Town antenna. NRAO/AUI image


[300 foot telescope after 1988 collapse]
300 foot after collapse, 1988. NRAO/AUI image


[GBT ground breaking]
GBT ground breaking, 1991. NRAO/AUI image


[Green Bank Telescope]
Green Bank Telescope. NRAO/AUI image


[Christening block at ALMA Camp ground breaking]
Alma Camp ground breaking. NRAO/AUI image


[ALMA]
ALMA. NRAO/AUI image


[4 NRAO Directors]
Lo, Vanden Bout, Roberts, Heeschen - 4 NRAO Directors at 50th anniversary. NRAO/AUI image


NATIONAL RADIO ASTRONOMY OBSERVATORY ARCHIVES

Records of the National Radio Astronomy Observatory: Item listing

36 Foot /12 Meter Telescope Unit


Title12 meter Telescope Correspondence - Miscellaneous Items
Start Date10/26/1977
End Date11/24/1987
Notes1 folder. Correspondence, memos, reports, photo
 [Range 3A]

TitleUpgrading the 36 ft Surface
Start Date1/9/1981
End Date8/7/1981
Notes1 folder. Correspondence, charts, diagrams, graphs
 [Range 3A]

TitleScheduling History
Start Date1/6/1982
End Date1/12/1987
Notes1 folder. Correspondence, charts
 [Range 3A]

Title12 meter Issues 1986-1989
Start Date9/26/1986
End Date9/14/1989
Notes1 folder. Correspondence, memos, meeting minutes; includes "Feasibility of Millimeter-Wave SIS Direct Detectors" by S. Weinreb 9/26/1986; "Coping with Flat Budgets in NRAO Operations" by R. L. Brown, April 1987; "A Proposal to Create a Prototype Intermediate Baseline Millimeter/Submillimeter Array" by Darrell Emerson et al, February 1988
 [Range 3A]

Title12 meter Closing - Letters of Protest and Support
Start Date10/11/1989
End Date12/20/1989
Notes1 folder. Correspondence
 [Range 3A]

Title12 meter Issues 1990-1995
Start Date1/2/1990
End Date6/9/1995
Notes1 folder. Correspondence, memos, reports
 [Range 3A]

Title12 meter Dome
Start Date12/14/1990
End Date10/2/1992
Notes1 folder. Correspondence, reports
 [Range 3A]

Title12 meter Survey
Start Date12/19/1995
Notes1 folder. Correspondence